Subscribe RSS Feed Email

Micro-surfacing road repairs begin Friday

June 13, 2024 3:03 PM
(Red Deer, Alberta)

Motorists are advised of upcoming traffic disruptions as crews work to repair arterial roadways throughout the city. The micro-surfacing product applied in previous years are being fixed under the warranty agreement with the contracted service provider.

“As with all roadway construction, micro-surfacing requires favourable conditions throughout the application and curing process. Unfortunately, some work completed last season did not have ideal conditions during curing and have experienced extensive deterioration. The contractor will be returning to repair these sections of roadway in June 2024 at no additional costs to the city as the work is under warranty,” said Lee Birn, Engineering Planning Superintendent for Parks and Public Works.

Including pothole repairs, spray patching, and crack sealing, micro-surfacing is an important preventative maintenance treatment that The City uses to slow down the ongoing wear and tear of Red Deer’s roadways. Micro-surfacing is a thin, yet durable surface treatment used to preserve existing asphalt roadways without the cost and inconvenience of fully removing and replacing the pavement surface.

Daytime lane reductions will be implemented as micro-surfacing repair work is underway in the following locations:

  • June 14: 19 Street, Spruce Drive - Complete
    • 19 Street westbound from Vermont Ave to 30 Avenue
    • Spruce Drive northbound, north of 37 Street
  • June 18: 32 Street west of Lockwood/Douglas Avenue
    • 32 Street from Metcalf Avenue/Allan Street to Lockwood Ave/Douglas Avenue
    • Excludes intersection on 32 Street and 30 Avenue
  • June 19: 32 Street at the Red Deer Polytechnic
    • 32 Street from 57 Avenue/College Boulevard to Taylor Drive
  • June 20-21: 32 Street and 40 Avenue intersection
    • To reduce impact to traffic, repair work will occur at the intersection of 32 Street and 40 Avenue overnight;
    • Work to begin by 8:30 p.m., June 20, and complete 7:00 a.m. on June 21.
  • June 20-21: 32 Street west of 40 Avenue
    • 32 Street eastbound and westbound from 47 Avenue to Springfield Avenue.
  • June 21-22: 40 Avenue from McBride Crescent to Anders Street/Spencer Street
    • Excludes 32 Street and 40 Avenue intersection.
  • June 22-23: 32 Street and 40 Avenue intersection
    • To reduce impact to traffic, repair work will occur at the intersection of 32 Street and 40 Avenue overnight;
    • Work to begin by 8:30 p.m., June 20, and complete 7:00 a.m. on June 21.

Motorists are advised to obey all signs and find an alternate route if possible. Please slow down when approaching or driving in a construction zone. Your patience and cooperation is greatly appreciated.

All construction dates are weather dependent and subject to change. For more information about road construction and closures visit reddeer.ca/roadclosures

- end -