Meter Upgrade Schedule

Residential and commercial electric meters will be upgraded throughout 2026 and 2027.

This spring, The City will begin replacing manually-read electric meters with new AMI meters. Meter replacement will be quick and easy, taking only a few minutes. Residents may notice a very brief power interruption. Learn more about how AMI Meters work here.

All customers will be receiving new AMI Meters, and installation will be rolled out neighbourhood-by-neighbourhood. 

Watch for AMI signage in your area.

Neighbourhood Schedule

A pilot installation program will begin this April in the communities of Capstone and West Park. We will be sharing specific neighbourhood-by-neighbourhood timelines in May. 

Neighbourhood Start Date Status
Capstone April 8  
West Park (north of Cronquist Drive) April 8