Meter Upgrade Schedule

Residential and commercial electric meters will be upgraded starting in spring 2026.

This spring, The City will begin replacing manually-read electric meters with new AMI meters. Meter replacement will be quick and easy, taking only a few minutes. Residents may notice a very brief power interruption. Learn more about how AMI Meters work here.

Neighbourhood Schedule

All residential and commercial customers will be receiving new AMI Meters, and installation will be rolled out neighbourhood-by-neighbourhood. Watch for AMI signage in your area and check the schedule below.

Neighbourhood Start Date Status
Capstone April 8 Completed
West Park (north of Cronquist Drive) April 8 Completed
Kentwood May 25  
Johnstone May 25  
Northwood Estates May 25