From April to October 2024, major utility upgrades will be constructed in the Grandview neighbourhood.
43 Ave/Ross St Utility Project
As part of The City of Red Deer 2024 Underground Utility Construction project, the water, sanitary and storm mains in a portion of Grandview are being upgraded. Construction started the week of March 18, 2024, and lane and road closures went into effect the week of April 1, 2024.
Road and rear lane closures are in effect, and detours around the work zones are required during the performance of this work.
The construction area includes:
- 43 Ave from Ross Street to 47 Street
- 43A Ave and 47 Street cul de sac
- Ross Street
Project Phases
Phase |
Dates* |
Description |
Progress |
Phase 1: 43A Ave & 47 St |
April 1 - July 30 |
Water Sanitary, and Storm infrastructure will be upgraded. The roadway will be excavated and rebuilt. One sidewalk will remain at all times for residents to use for transportation. Temporary parking on 43 Ave will be established for residents impacted. |
- Paving is complete.
- Landscaping restoration to be completed by October 15.
|
Phase 2: Ross St. (North) Intersection |
June 15 - July 30 |
Water, Sanitary, and Storm infrastructure will be upgraded along with upgraded traffic infrastructure and signals. Traffic pattern will change on Ross Street to one West bound lane and one East bound lane on the south side of Ross Street |
- Paving is complete.
- Landscaping restoration to be completed by October 21.
|
Phase 3: Ross St. (South) Intersection |
July 15 - Sept. 15 |
Water, Sanitary, and Storm infrastructure will be upgraded along with upgraded traffic infrastructure and signals. Traffic Pattern will change on Ross Street to one West bound lane and one East bound lane on the north side of Ross Street. |
- Road subgrade is now complete.
- Paving to be completed by October 17.
|
Phase 4: 43 Ave |
Aug. 15 - Oct. 30 |
Water, Sanitary, and Storm infrastructure will be upgraded. 43 Avenue will be closed at this time. Detours around 43 Avenue will be in place. Access to apartment building will be from east bound Ross Street. |
- Paving to be completed by October 21.
- Landscaping restoration to be completed by October 25.
|
*dates are weather dependent